Time flies with great content! Renew in to keep enjoying all our premium content.
Prime
Sh2bn Ketraco and Chinese firm row sent to arbitration
The Chinese firm says the initial contract sum was Sh3.3 billion and that the job was to be implemented within 22 months starting February 14, 2017. The completion date was expected to be December 2018.
The High Court has referred a Sh2.18 billion dispute between a Chinese firm and state-owned Kenya Electricity Transmission Company Ltd (Ketraco) to arbitration.
Justice Peter Mulwa further declined to issue any orders as sought by North China Power Engineering Company Limited, saying it would not be proper to restrain Ketraco from dealing with a “critical transnational infrastructure project which would not only harm public interest but also Kenya’s energy security”.